Project planning: scope, timelines and the critical path

13 minute read · 6-question quiz

Download this lesson as a colour Word or PDF study guide with the figures and answers. Included in paid plans; reading and quizzes stay free.Sign in

What you will learn

  • Define scope, deliverables and milestones for a clinical trial project

  • Build a simple timeline and find the critical path

  • Use a Gantt chart and manage changes to scope

A clinical trial is a project: a temporary effort with a defined start and end, a goal, a budget and a team. Project management applies planning and control so that the trial delivers its objectives on time, within budget and to the required quality.

The project triangle

Three linked constraints are scope, time and cost, with quality at the centre. Changing one affects the others. Adding sites (scope) usually costs more and may speed enrolment, but also adds complexity.

Defining scope

A clear scope statement lists what the project will deliver: number of sites and countries, number of participants, visits, services provided (monitoring, data management, statistics, regulatory, medical writing) and what is excluded. The contract and work order record it, and any change goes through a change order with agreed cost and time impact.

Work breakdown and milestones

A work breakdown structure (WBS) divides the project into manageable parts: start-up, recruitment, conduct, data management, safety, close-out and reporting. Each has tasks, owners and dates. Milestones are key points such as ethics approval, first site activated, first participant in, last participant in, last participant last visit, database lock and final report.

Month 0Contract signedMonth 5Approvals and firstsite activeMonth 6First participant inMonth 20Last participant inMonth 32Last visit, thendatabase lock
Typical milestones of a trial. Delays in early milestones push every later one.

Critical path

Some tasks must finish before others start. The critical path is the longest chain of dependent tasks, which sets the minimum project duration. A delay in any critical task delays the whole project, while non-critical tasks have float (slack).

For example, if ethics review (8 weeks) and regulatory review (10 weeks) run in parallel, only the longer (regulatory) is on the critical path. Shortening ethics review does not speed up the project unless the regulatory path also shortens.

Gantt charts

A Gantt chart shows tasks as bars along a time axis, with dependencies, milestones and progress. It makes it easy to see overlaps, critical tasks and delays.

Worked example: finding the critical path

A start-up has the following tasks (weeks).

  • A: Write documents, 6. No predecessor.
  • B: Ethics review, 8. After A.
  • C: Regulatory review, 10. After A.
  • D: Import permit, 4. After C.
  • E: Train staff and set up site, 5. After B.
  • F: Site initiation, 2. After D and E.

Path 1: A, B, E, F = 6 + 8 + 5 + 2 = 21 weeks.

Path 2: A, C, D, F = 6 + 10 + 4 + 2 = 22 weeks.

Path 2 is the critical path (22 weeks). Path 1 has 1 week of float. If the regulatory review slips by 3 weeks, the project finishes in 25 weeks. If ethics review slips by 1 week, the project is unaffected.

01020Weeks21Path 1: ethics path22Path 2: regulatory path (critical)
The longer path sets the duration. The shorter path has 1 week of float.

Manage the critical path actively

Review the critical path every week. Add resources or remove obstacles on critical tasks first. Tasks with float can be rescheduled if needed.

Scope creep

Small unplanned additions (extra visits, extra reports, extra countries) accumulate and break budgets and timelines. Route every request through a change control process.

Check yourself

List the five longest steps in start-up for your next study. Which depend on someone outside your team?

Summary

  • A trial is a project with scope, time, cost and quality constraints.

  • A WBS, milestones and a Gantt chart organise work.

  • The critical path is the longest dependent chain and sets the minimum duration.

  • Change orders control scope creep.

Check your understanding

Question 1
1

The critical path is:

Question 2
2

Float is:

Question 3
3

In the example, path 1 is 21 weeks and path 2 is 22 weeks. The project duration is:

Question 4
4

A change order is used to:

Question 5
5

A milestone is:

Question 6
6

Scope creep describes: